TYPE OF PILLARS

Ground Control 0 Comment

SINGLE SQUARE CHAIN DESIGN The load transferred from the adjacent goaf areas is dependent upon the depth of cover to satisfy subsidence compatibility. For sub-critical subsidence conditions the following expression is used to calculate the load supported by a pillar: for w/h < 2 tan f Where : w = […]

Read More  

CHAIN PILLAR DESIGN

Ground Control 0 Comment

The diagram opposite shows a typical longwall panel with a single row of rectangular chain pillars. Chain pillars can be either square, rectangular or in some case diamond in shape. They can also be in a single or double row configuration. In Australia a single line of rectangular chain pillars is the […]

Read More  

OPTIMAL MINING DIRECTION

Ground Control 0 Comment

Lateral stress is thought to be generated by techtonic plate movements. The magnitude of lateral stress undergound is proportional to rock stiffness since the stress is induced by constant lateral dispalcement. Since the stress can not pass through the openinigs, it will concentrate around them. The optimal direction of drivage […]

Read More  

ABUTMENT PRESSURES

Ground Control 0 Comment

In the diagram opposite, mining of a longwall panel results in the formation of front and side abutment pressures. The peak of the front abutment pressures can occur 1 to 3 metres ahead of the face and the extent of the front abutment pressures can be up to 50 metres […]

Read More  

GROUND CONTROL OVERVIEW

Ground Control 0 Comment

Longwall mining activities alter the exsisting ground stress field, this changed stress field is known as induced stress. Extraction of coal by longwall mining induces a redistribution of stresses causing the rocks near the mining excavation to accomodate a redistributed load. Effective and efficient longwall mining is dictated by the […]

Read More  

RECOVERY

Change Out 0 Comment

Set up for Recovery Set the Armoured Face Conveyor (AFC) and the Beam Stage Loader (BSL) chains and break them. The maingate drive is disconnected from the BSL mini pans and AFC pans by removing the dog bone connector at the maingate drive. Removing the Pantechnicon The pantechnicon consist of […]

Read More  

BOLT UP SEQUENCE

Change Out 0 Comment

Bolt Up Sequence Stage 1 Cut from the tailgate in 20 chock sections. Place 1 “w” strap over the top of the chock (ie perpendicular to the face) anchored with 2 bolts set at 6.8 metres. Set rows 1 & 3 after row 2 at 7.3 metres & 6.3 metres. […]

Read More  

BOLT UP CYCLE

Change Out 0 Comment

The bolting up cycle is the first major procedure in the recovery of the longwall. The purpose of the bolting up cycle is to provide a safe working environment for the recovery of equipment by providing support to the longwall face. Support is provided to the roof, face, maingate and […]

Read More  

CRITICAL PATH

Change Out 0 Comment

HUESKER SYSTEM

Change Out 0 Comment
VIDEO DEMONSTRATION Please choose your preferred video file Dial up (approx 14.9 MB) ADSL, ISDN or similar Broadband (approx 21.8 MB) High speed Broadband (approx 76.5 MB) Video’s Courtesy of NBW Mining Australia Read More